I-25 / Paseo Del Norte Interchange
Scope:
The purpose of this project is the reconstruction of I-25 / Paseo Del Norte Interchange.  The project will predominately focus on improving traffic flow for the northbound I-25 to westbound Paseo Del Norte (NM 423) and eastbound Paseo Del Norte to southbound I-25 movements.  The project will also include grade separation at Jefferson Street and Paseo Del Norte Boulevard intersection, mainline improvements on I-25 between Jefferson and Alameda, enhance bicycle connectivity in the area, signing, striping, lighting, aesthetics, and other miscellaneous improvements.   

Estimated Project Cost: $93 Million

Project Sponsor:
NMDOT /City of Albuquerque (COA) 
Hooshang Tavanaiepour, Project Development Engineer 505-798-6723

Project Comments: 
I-25 / Paseo Del Norte Project
C/O Scott Perkins 
Wilson & Company, Inc.
4900 Lang Avenue NE
Albuquerque, New Mexico 87109
SFperkins@wilsonco.com


NM 528 Pat D’Arco Highway Improvement Project
Scope:  Reconstruction and improvement of NM 528 (Pat D’Arco Highway) from Southern Boulevard to Northern Boulevard.  The project will be done in phases based on the amount of funding that is available.  Planned improvements include reconstructing/rehabilitating the existing pavement, widening to three continuous driving lanes in each direction, adding left and right turn lanes at all intersections, adding continuous on-street bike lanes in each direction, frontage road improvements in the Industrial Park area, replacing the multi-use trail and extending it to Northern Boulevard upgrading traffic signal equipment and sidewalk ramps to comply with the Americans with Disabilities Act (ADA), modifying access to improve highway operations and safety, installation of a storm sewer system, and noise mitigation. 

Estimated Project Cost:
$12 Million – Phase I, Southern Blvd. to Ridgecrest Dr.
$16 Million – Phase 2, Ridgecrest Dr. to Northern Blvd.

Project Sponsor:
NMDOT
Rais Rizvi, P.E. – Project Development Engineer 505-798-6710 Rais.rizvi@state.nm.us
Consultant:   
Parsons Brinkerhoff
Hal Byrd – Project Manager
6100 Uptown Blvd., N.E. Suite 700
Albuquerque, NM 87110
(505)881-5357
byrd@pbworld.com

Project Documents:


I-40 Rio Puerco Interchange to Nine Mile Hill
Scope:  Roadway reconstruction to include eastbound climbing lane extension and installation of pavement performance data collection station.

Project Amount: $12.5 million
Anticipated Start Date: February 2012
Expected Completion Date: September 2012

Project Sponsor
NMDOT
Tim Chavez, Project Manager 505-798-6600
Contractor:
Mountain States Constructors
2341 Pan American Freeway NE # 112
Albuquerque, NM 87107
(505) 292-0111


I-25, Comanche to Jefferson
Scope:    Auxiliary lane extension between Comanche and Jefferson

Approximate Cost:  $1.94 million
Anticipated Start Date: April 2012
Expected Completion Date: August 2012

Project Sponsor:
NMDOT
Justin Gibson, Project Manager 505-798-6600


NM 6, between I-25 and NM 314
Scope: Sidewalk and curb upgrades

Project Amount:  $320,000
Anticipated Start Date:  February 2012

Project Sponsor:
NMDOT
Justin Gibson, Project Manager 505-798-6600
Contractor:
G. Sandoval Construction, Inc.
2000 E. Lohman Ave. Ste. B
Las Cruces, NM 88001
(575)524-6878


NM 313, Sandia Pueblo to U.S. 550
Scope: Pavement preservation project – mill and inlay of driving lanes

Project Amount:  $1.1 million
Anticipated Start Date:  October 2012
Expected Completion Date: November 2012

Project Sponsor:
NMDOT
Jay Loomis, Project Manager 505-798-6600
Contractor:
Fisher Sand and Gravel
PO Box 8340
Placitas, NM 87043
867-2600


I-25, U.S. 550 to Algodones
Scope:    Pavement Preservation project - mill and inlay of driving lanes

Project Amount: $3.3 million
Anticipated Start Date: April 2012
Expected Completion Date: August 2012

Project Sponsor:
NMDOT
Jay Loomis, Project Manager 505-798-6600
Contractor:
Mountain States Constructors
2341 Pan American Freeway NE # 112
Albuquerque, NM 87107
(505) 292-0111


I-40 and Rio Puerco Interchange
Scope:
Construction of a new bridge over I-40, roundabout on the north side of I-40 at the intersection of the frontage road and the bridge crossing over the Interstate, drainage improvements, pedestrian, bicycle, and ADA upgrades. 

Estimated Project Cost: $6 million

Documents:

Project Sponsor:
NMDOT
Hooshang Tavanaiepour, Project Development Engineer 505-798-6723
Consultant:
Chris Baca
Vector Engineering
5951 Jefferson Street, NE Suite B
Albuquerque, NM  87109
(505) 341-9393
cbaca@vectornm.com


U.S. 60
Scope:    Roadway reconstruction between mile marker 170 and 176, to include shoulder widening, drainage improvements, access management, signing and striping.

Estimated Project Cost: $8.5 million

Project Sponsor:
NMDOT
Leslie Fortier, Project Development Engineer 505-222-6775


I-25/US 550 Interchange Reconstruction Project
Scope:    The I-25/US 550 Interchange Reconstruction project will modify the Interstate 25 (I-25) and US 550 interchange and portions of US 550 and NM 165 on either side of the interchange to enhance regional mobility by improving traffic performance at the I-25/US 550 interchange  Additionally, the projects goal is to mitigate congestion and improve access along US 550 from NM 313 to I-25 while creating  a roadway system that is compatible with and that promotes the needs and interests of the community and other highway users and stakeholders.  
Project Sponsor:
NMDOT
Hooshang Tavanaiepour, Project Development Engineer 505-798-6723
Projects Documents:
Public Meeting – November 9, 2010 Handout/Presentation Packet
Public Meeting - March 8, 2011 Handout/Presentation Packet
Public Hearing – October 4, 2011 Meeting Handout Environmental Document PDF
FONSI | Request Letter
Input Synopsis

Project Comments: 
I-25/US 550 Project
C/O Dawn Tibbetts
Parsons Brinckerhoff
6100 Uptown Blvd., Suite 700
Albuquerque, NM  87110
tibbettsD@pbworld.com


NM 47 Peralta Roadway Improvements Project
Scope: The New Mexico Department of Transportation (NMDOT) is conducting the NM 47 Peralta Corridor Study to develop and evaluate alternatives for improving NM 47 from milepost (MP) 31.0 at Valencia Road to MP 32.8 located approximately 285 feet north of the Peralta Post Office.  The goal of the project is to develop and evaluate alternatives that would correct existing roadway and drainage deficiencies, address roadway congestion, and improve safety conditions.

Project Sponsor:
NMDOT
Paul Lindberg, Project Development Engineer, paul.lindberg@state.nm.us

Project Documents:
Property Onwer Interview Workshop 03-31-2012
Public Information Meeting Handout – September 6, 2011
Public Information Meeting Handout – February 15, 2012
Proposed Typical Section and Plan Figures (31 MB PDF)
Final Phase A/B Location and Environmental Study (23 Mb PDF)

Project Comments:
NM 47 Peralta Project
c/o Eric Johnson
Marron and Associates
7511 4th Street NW
Albuquerque, NM  87107
eric@marroninc.com