NMDOT Home Page

NMDOT Road Construction Projects

District Reference Map

District 6

Larry Maynard, P.E.
District Engineer

P.O. Box 2160
Milan, NM 87021
Telephone: 505-285-3206
Toll Free: 800-361-3596
E-Mail


Allison Road Corridor and Interstate 40 Interchange Project (CN C6121610 & CN6100610)

Scope: This is a corridor improvement project in the City of Gallup, McKinley County, New Mexico. Funding limitations preclude design and construction of the proposed projects as one project. The proposed alignment lends itself to being constructed in several phases rather than requiring development of the entire corridor as one project. The project limits along I-40 are milepost (MP) 19.3 to MP 20.2. The northern limits of the study corridor are Acoma Street and Cortez Road, Kachina Street, and West Maloney Avenue north of the interstate and the southern limits are New Mexico (NM) 118 and Barbara Avenue.

Estimated Project Cost:

  1. Rio Puerco Bridge $4,800,000: $280,000 – design only. City ($210,000) and NMDOT ($170,000)
  2. BNSF & NM 118 Overpass $7,750,000: Reprogrammed to 2016 STIP
  3. I-40 Overpass $3,025,000: None Identified
  4. Acoma & Maloney Connection $3,020,000: None Identified
  5. Kachina Connection $2,875,000: None Identified
  6. I-40 Interchange $2,870,000: None Identified

Project Sponsor:
NMDOT District 6
Bryan Peters, District 6 Technical Support Engineer, 505.285-3200
Stephen Lopez, Project Development Engineer, 505.798-6721

Project Documents:


I-40, Roadway Rehabilitation (CN 6100712)

Scope:  This is a pavement preservation project in Cibola County, west of Milan from mile marker 69.00 to 75.00.  Construction consists of milling and inlaying with HMA and placement of OGFC.

Estimated Project Cost: $5.4 Million

Project Sponsor:
NMDOT
Johnny Gallegos, Project Manager (505) 285-6837

Contractor:
FNF Construction, Inc.
115 S. 48th Street
Tempe, AZ 85281
(480) 784-2910


NM 118/NM 122/NM 197, Bridge Rehabilitation (CN 6100822)

Scope:  This project is located on NM 118, mile marker 8.024 (Defiance) in McKinley County; NM 122, mile marker 37.558 (East Grants) in Cibola County; and NM 197, mile marker 6.532 (west of Cuba) in Sandoval County.  Construction consists of bridge preservation.

Engineer's Estimate:  $260,714.00

Project Sponsor:
NMDOT
Johnny Gallegos, Project Manager (505) 285-6837

Contractor:
Villalobos Construction
5130 Oriole Road
Las Cruces, NM 88011
(575) 532-8041


I-40/NM 6 Intelligent Transportation System (CN 6100180)

Scope:  This project is located in Cibola County along I-40, mile marker 126.700, near Exit 126 and NM 6, north of the Highland Meadows Community.  Construction consists of installation of a dynamic message board, camera and remote weather information system (RWIS).

Engineer's Estimate:  $630,333.00

Project Sponsor:
NMDOT
Johnny Gallegos, Project Manager (505) 285-6837

Contractor:
MWI, Inc.
2303 Phoenix Ave., NE
Albuquerque, NM 87190
(505) 808-0744


Various Locations in District Six, Stockpiling (CN 6100294)

Scope:  This project consists of stockpiling chip seal and base course materials at various sites in San Juan, Cibola, McKinley and Sandoval Counties.

Engineer's Estimate:  $924,700.00

Project Sponsor:
NMDOT
Johnny Gallegos, Project Manager (505) 285-6837

Contractor:
Mountain States Constructors, Inc.
3601 Pan American Fwy., NE, Suite 111
Albuquerque, NM 87107
(505) 292-0108


I-40/US 550, Bridge Rehabilitation (CN M600333)

Scope:  This project is located along I-40, mile marker 80.009, just east of Milan; mile marker 102.185, near Sky City Casino; and on US 550, mile marker 11.792, north of Bernalillo.  Construction consists of bridge preservation.

Engineer's Estimate:  $228,228.00

Project Sponsor:
NMDOT
Johnny Gallegos, Project Manager (505) 285-6837

Contractor:
The Truesdell Corporation
1310 W. 23rd Street
Tempe, AZ 85282
(602) 437-1711


US 60, Roadway Rehabilitation (CN 6100451)

Scope:  This is a pavement preservation project in Catron County, west of Datil from mile marker 69.00 to 73.00.  Construction consists of milling and inlaying with HMA and placement of OGFC.

Estimated Project Cost:  $1.7 Million

Project Sponsor:
NMDOT
Robert Darby, Project Manager (505) 285-6829

Contractor:
Russel Sand & Gravel Co.
P.O. Box 296
Los Ojos, NM 87551
(575) 588-7933


I-40, Safety (CN M600217)

Scope:  This project is located in McKinley County along I-40 at the Thoreau Interchange, mile marker 53.069 to 53.477.  Construction consists of installation of vehicle impact attenuators and concrete wall barrier.

Estimated Project Cost:  $325,885.00

Project Sponsor:
NMDOT
Robert Darby, Project Manager (505) 285-6829

Contractor:
G. Sandoval Construction
2000 E. Lohman Ave., Suite B
Las Cruces, NM 88001
(575) 524-6878


US 550, Bridge Rehabilitation (CN 6100501)

Scope:  This Project is located along US 550, mile marker 53.666 to 53.734 in Sandoval County, south of Cuba, NM.  Construction consists of grout injection, compaction and bridge preservation.

Engineer's Estimate:  $1.1 Million

Project Sponsor:
NMDOT
Robert Darby, Project Manager (505) 285-6829

Contractor:
AUI, Inc.
P.O. Box 9825
Albuquerque, NM 87105
(505) 242-4848


Various Locations in District Six, Crack Sealing District-Wide (CN 6100297)

Scope:  This is a pavement preservation project located in various locations in McKinley, Cibola and Catron Counties.  Construction consists of crack sealing various roadways, district-wide.

Estimated Project Cost:  $1.4 Million

Project Sponsor:
NMDOT
Robert Darby, Project Manager (505) 285-6829

Contractor:
Cactus Transport, Inc.
5408 Edith Blvd., NE
Albuquerque, NM 87107
(505) 341-9691


US 550/NM 197, Lighting (CN 6100770)

Scope:  This project is located at the intersection of US 550 and NM 197 in Cuba, NM.  Construction consists of installation of lighting.

Estimated Project Cost:  $75,657.00

Project Sponsor:
NMDOT
Robert Darby, Project Manager (505) 285-6829

Contractor:
MWI, Inc.
2303 Phoenix Ave., NE
Albuquerque, NM 87190
(505) 808-0744


I-40, Roadway Rehabilitation (CN 6100560)

Scope:  This is a pavement preservation project located in McKinley County along the eastern Gallup City Limits from mile marker 24.6 to 29.7.  Construction consists of milling and inlaying with HMA and placement of OGFC.

Estimated Project Cost:  $5.2 Million

Project Sponsor:
NMDOT
Jeremiah Herrera, Project Manager (505) 722-9498

Contractor:
FNF Construction, Inc.
115 S. 48th Street
Tempe, AZ 85281
(480) 784-2910


US 491, Roadway - New Construction (CN 6100780)

Scope:  This is a roadway construction project located in San Juan County, north of Sheep Springs from mile marker 41.854 to 46.000.  Construction consists of the construction of two additional northbound lanes.

Estimated Project Cost:  $11.5 Million

Project Sponsor:
NMDOT
Jeremiah Herrera, Project Manager (505) 722-9498

Contractor:
Skanska, USA Civil West Rocky Mountain
P.O. Box 1660
Cortez, CO 81321
(970) 529-2103


I-40/US 491, Bridge Rehabilitation (CN 6100821)

Scope:  This project is located along I-40, mile marker 11.403 (west of Gallup); and along US 491, mile marker 0.01 to 0.560 (Munoz Overpass in the City of Gallup) in McKinley County.  Construction consists of bridge preservation.

Engineer's Estimate:  $633,880.00

Project Sponsor:
NMDOT
Jeremiah Herrera, Project Manager (505) 722-9498

Contractor:
Villalobos Construction
5130 Oriole Road
Las Cruces, NM 88011
(575) 532-8041


US 491, Roadway-New Construction (CN 6100781)

Scope:  This is a roadway construction project located in McKinley County, north of Buffalo Springs from mile marker 36.962 to 42.427.  Construction consists of the construction of two additional northbound lanes.

Estimated Project Cost:  $13 Million

Project Sponsor:
NMDOT
Jeremiah Herrera, Project Manager (505) 722-9498

Contractor:
Mountain States Constructors, Inc.
3601 Pan American Fwy., NE, Suite 111
Albuquerque, NM 87107
(505) 292-0108


I-40, Roadway Rehabilitation (CN 6100716)

Scope:  This project is located along I-40, mile marker 35.077 to 38.186, near Ciniza Refinery in McKinley County.  Construction consists of milling and inlaying with HMA and placement of OGFC.

Engineer's Estimate:  $4.9 Million

Project Sponsor:
NMDOT
Jeremiah Herrera, Project Manager (505) 722-9498

Contractor:
Fisher Sand & Gravel, New Mexico Incorporated
30A Frontage Rd., East
Placitas, NM 87043
(505) 867-2600


I-40/NM 118, Ramp Reconstruction (CN 6100222)

Scope:  This project is located in McKinley County at the Iyanbito Interchange, mile marker 36.  Construction consists of replacing the bridge over I-40 and lengthening the ramps.

Estimated Project Cost:  $5.2 Million

Project Sponsor:
NMDOT
Frank Salazar, Project Manager (505) 722-4903

Contractor: 
FNF Construction, Inc.
115 S. 48th Street
Tempe, AZ 85281
(480) 784-2910


I-40/US 491, Roadway Reconstruction (CN 6100801)

Scope:  This project is located at the intersection of I-40 and US 491 (Munoz Interchange) in McKinley County.  Construction consists of geometry improvements on West Maloney.

Estimated Project Cost:  $890,476.72

Project Sponsor:
NMDOT
Frank Salazar, Project Manager (505) 722-4903

Contractor: 
AUI, Inc.
P.O. Box 9825
Albuquerque, NM 87105
(505) 242-4848


I-40, Roadway Rehabilitation (CN 6100630)

Scope:  This project is located along I-40, mile marker 17.900 to 22.200, west Gallup in McKinley County.  Construction consists of milling and inlaying with HMA and placement of OGFC.

Estimated Project Cost:  $4.1 Million

Project Sponsor:
NMDOT
Frank Salazar, Project Manager (505) 722-4903

Contractor: 
Fisher Sand & Gravel, New Mexico Incorporated
30A Frontage Rd., East
Placitas, NM 87043
(505) 867-2600